Project of the Year 2007: Overall Winner
New York
Times
Building
Owner: New York Times/ ForestCityRatner Cos., New York
Architect: Gensler
Construction Manager: Turner Construction, New York
Flooring Sub-Contractor: Pyramid Floor Covering, Inc.
Scope: Pour Drytek 7200 self-leveling underlayment with leveling pegs at ¾” average on fifteen floors.
Project of the Year 2007: Interior Fit-Out
The Institute for the Study of the Ancient World
Architect: Selldorf Architects, New York
Construction Manager. EW Howell
Flooring Sub-Contractor: Pyramid Floor Covering, Inc.
Scope: Drytek 920 wear surface self-leveling underlayment at ¾” average pour at specific locations throughout the project
Project of the Year 2007: Cultural Institutions/ Theaters/ Museums
New Museum of Contemporary Art
Architect: Gensler
Construction Manager: F. J. Sciame Construction Co., Inc.
Flooring Sub-Contractor: Pyramid Floor Covering, Inc.
Scope: Resilient flooring.
Project of the Year 2007: Retail
Uniqlo Flagship
Architect: Greenberg Farrow
Construction Manager: Richter + Ratner, New York
Flooring Sub-Contractor: Pyramid Floor Covering, Inc.
Scope: Resilient flooring
Project of the Year 2007: Research Facility
Center for Functional Nanomaterials at Brookhaven National Laboratory
Architect: HDR Architecture
Construction Manager: EW Howell
Flooring Sub-Contractor: D.A.G. Floors/ Installation by Pyramid Floor Covering, Inc.
Scope: Linoleum, rubber tile, rubber roll goods with heat weld and flash cove, vinyl enhanced tile and carpet tile.
Project of the Year 2007: Higher Education
Joan and JoelSmilowResearchCenter at NYUSchool of Medicine
Construction Manager: Turner Construction, New York
Architect: Mitchell Giurgola Architects
Flooring Sub-Contractor: D.A.G. Floors/ Installation by Pyramid Floor Covering, Inc.
Scope: Resilient flooring work
Project of the Year 2007: Health Care/ Hospitals
Hospital for Special Surgery
Architect: Cannon Design